Location |
No. 77 Ko Shan Road, Hung Hom, Kowloon |
Construction Commencement |
21 January 2011 |
Construction Completion |
17 December 2013 |
Client Department |
Leisure and Cultural Services Department, HKSARG |
Site area |
4,000 sq.m. |
Construction Floor area |
10,538 sq.m. |
Project Manager |
Architectural Services Department, HKSARG |
Architect |
Ronald Lu & Partners |
Structural & Geotechnical Engineer |
Mott MacDonald Hong Kong Ltd. |
Building Services Engineer |
Electrical and Mechanical Services Trading Fund, HKSARG |
Landscape Architect |
ACLA Limited |
Quantity Surveyor |
Rider Levett Bucknall Ltd. |
Town Planner |
PlanArch Consultants Ltd. |
Environmental Consultant |
Allied Environmental Consultants Ltd. |
Theatre and Acoustic Consultant |
Shen Milsom & Wilke, Ltd |
Main Contractor |
Gammon Construction Limited |